EMERGING TRENDS IN SOFTWARE ENGINEERING
MISCELLANEOUS
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
True
|
|
False
|
|
Either A or B
|
|
None of the above
|
Detailed explanation-1: -One can choose Waterfall Model if the project development schedule is tight. Explanation: Real projects rarely follow the sequential flow and iterations in this model are handled indirectly. This changes can cause confusion as the project proceeds thereby delaying the delivery date.
Detailed explanation-2: -Waterfall Model: No working software is produced until late during the life cycle. We can not go back to the previous project phase as soon as we proceed to the next phase, So inflexible. Hence the correct answer is the Waterfall model.
Detailed explanation-3: -The waterfall model is most commonly used in software engineering and product development, less often – in other projects and industries. Employ the waterfall model only if your project meets the following criteria: All the requirements are known, clear, and fixed. There are no ambiguous requirements.