SOFTWARE ENGINEERING

EMERGING TRENDS IN SOFTWARE ENGINEERING

MISCELLANEOUS

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Suppose that a project was estimated to be 3000 LOC. Calculate the effort, development time, average staff size and productivity of the project
A
8.2 PM, 5.4 M, 1.4 P, 0.395 KLOC/ PM
B
7.6 PM, 4.9 M, 1.4 P, 0.395 KLOC/ PM
C
7.6 PM, 5.4 M, 1.4 P, 395 LOC/ PM
D
7.6 PM, 4.9 M, 1.4 P, 395 KLOC/ PM
Explanation: 

Detailed explanation-1: -COCOMO II Estimation Process The formula for the process is given by: ffort (P )=A Size B 0.01 ∑ S j j=1. Software cost estimation is a challenging and onerous task. Estimation by analogy isone of the expedient techniques in software effort estimation field.

Detailed explanation-2: -Person Required = effort/time a, b, c, d are constants and have different values for different models. Time is the time required to develop the product and the unit is months. And the effort is the total effort calculated that will be required to complete the work calculated in PM (Person Months).