Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Testing activities should start during
A
Design
B
Implementation
C
System testing
D
Maintenance
Explanation: 

Detailed explanation-1: -CORRECT ANSWER : as soon as possible in the development lifecycle.

Detailed explanation-2: -The Test case development begins once the test planning phase is completed. This is the phase of STLC where testing team notes the detailed test cases. Along with test cases, testing team also prepares the test data for testing.

Detailed explanation-3: -Software testing should start early in the Software Development Life Cycle. This helps to capture and eliminate defects in the early stages of SDLC i.e requirement gathering and design phases. An early start to testing helps to reduce the number of defects and ultimately the rework cost in the end.

Detailed explanation-4: -Requirement Analysis. Test Planning. Test Case Designing and Development. Test Environment Setup. Test Execution. Test Closure. 03-Feb-2023