Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
The activity that distributes estimated effort across the planned project duration by allocating the effort to specific software developing task is ____
|
Project Scheduling
|
|
Detailed schedule
|
|
Macroscopic schedule
|
|
None of the above.
|
Explanation:
Detailed explanation-1: -Project scheduling is an activity that distributes estimated effort across the planned project duration by allocating the effort to specific software engineering tasks.
Detailed explanation-2: -Explanation: a recommended distribution of effort across the software process is 40% (analysis and design), 20% (coding), and 40% (testing).
Detailed explanation-3: -Task network ( activity network ) is a graphic representation of the task flow for a project. o The task network depicts major software engineering tasks. ยท Parallel tasks occur asynchronously. o Planner must determine intertask dependencies to ensure continuous progress toward completion.