The activity that distributes estimated effort across the planned project duration by allocating the effort to specific software developing task is ____
A
Project Scheduling
B
Detailed schedule
C
Macroscopic schedule
D
None of the above.
Explanation: 

Detailed explanation-1: -Project scheduling is an activity that distributes estimated effort across the planned project duration by allocating the effort to specific software engineering tasks.

Detailed explanation-2: -Explanation: a recommended distribution of effort across the software process is 40% (analysis and design), 20% (coding), and 40% (testing).

Detailed explanation-3: -Task network ( activity network ) is a graphic representation of the task flow for a project. o The task network depicts major software engineering tasks. ยท Parallel tasks occur asynchronously. o Planner must determine intertask dependencies to ensure continuous progress toward completion.