The Project Management model can sometimes make it difficult for the test to initiate any change in requirements.
A
Agile model
B
Waterfall model
C
Either A or B
D
None of the above
Explanation: 

Detailed explanation-1: -In Waterfall, the testing phase happens after the building phase. This means clients must be concise and clear on requirements before development begins. Once the project begins, there cannot be any changes made. Other phases of development, like design or testing, have to be complete once in Waterfall as well.

Detailed explanation-2: -What is waterfall project management? The waterfall project management approach entails a clearly defined sequence of execution with project phases that do not advance until a phase receives final approval. Once a phase is completed, it can be difficult and costly to revisit a previous stage.