SOFTWARE ENGINEERING

EMERGING TRENDS IN SOFTWARE ENGINEERING

MISCELLANEOUS

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
The quickest time in which a task may be completed under perfect conditions is referred to as
A
The most pessimistic time estimate
B
The most optimistic time estimate
C
The expected time estimate
D
The most likely time estimate
Explanation: 

Detailed explanation-1: -The shortest possible time in which an activity can be achieved under ideal circumstances is known as the optimistic time estimate. Explanation: According to the time estimates made by the PERT planners, the maximum time that would be needed to complete an activity is called the pessimistic time estimate.

Detailed explanation-2: -Duration is defined as the entire time taken to complete an activity, based on the resources allocated to the project.

Detailed explanation-3: -Optimistic time: This is to estimate the minimum possible time in which an activity can be completed in an ideal condition. In other words it the shortest time for the completion of an activity. It is denoted by to.

There is 1 question to complete.