 Question 
 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
 
 | 
 What is pert analysis based on? 
| 
 | 
  Optimistic time 
 
 | 
| 
 | 
  pessimistic time 
 
 | 
| 
 | 
  Most likely time 
 
 | 
| 
 | 
  all of the above 
 
 | 
 Explanation: 
Detailed explanation-1: -PERT analysis is based on optimistic time, pessimistic time and most likely time.
Detailed explanation-2: -Pessimistic time is a concept used in the program evaluation and review technique (PERT). It represents the longest estimated time period within which a task is likely to be completed, and is used in project management activities.
Detailed explanation-3: -In PERT the individual activity follows – distribution but the total project duration follows normal distribution. So the – distribution cannot be divided into equal halves by probable time. But the expected duration of the project divide the total project duration by two equal halves.