Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
What is pert analysis based on?
A
Optimistic time
B
pessimistic time
C
Most likely time
D
all of the above
Explanation: 

Detailed explanation-1: -PERT analysis is based on optimistic time, pessimistic time and most likely time.

Detailed explanation-2: -Pessimistic time is a concept used in the program evaluation and review technique (PERT). It represents the longest estimated time period within which a task is likely to be completed, and is used in project management activities.

Detailed explanation-3: -In PERT the individual activity follows – distribution but the total project duration follows normal distribution. So the – distribution cannot be divided into equal halves by probable time. But the expected duration of the project divide the total project duration by two equal halves.