What is pert analysis based on?
|
Optimistic time
|
|
pessimistic time
|
|
Most likely time
|
|
all of the above
|
Explanation:
Detailed explanation-1: -PERT analysis is based on optimistic time, pessimistic time and most likely time.
Detailed explanation-2: -Pessimistic time is a concept used in the program evaluation and review technique (PERT). It represents the longest estimated time period within which a task is likely to be completed, and is used in project management activities.
Detailed explanation-3: -In PERT the individual activity follows – distribution but the total project duration follows normal distribution. So the – distribution cannot be divided into equal halves by probable time. But the expected duration of the project divide the total project duration by two equal halves.