Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
What is the duration of Agile-Scrum meeting?
A
Depends on project Complexity
B
1 hour
C
Depends on Scrum Master
D
15 minutes
Explanation: 

Detailed explanation-1: -The Daily Scrum is a 15-minute event for the Developers of the Scrum Team. To reduce complexity, it is held at the same time and place every working day of the Sprint. If the Product Owner or Scrum Master are actively working on items in the Sprint Backlog, they participate as Developers.

Detailed explanation-2: -Duration: Typically 45 minutes per week of iteration-e.g. a 90-minute retrospective after a two-week sprint. Agile framework: Scrum and kanban.

Detailed explanation-3: -Scrum Reference Card Excerpt: Daily Scrum and Sprint Execution. Every day at the same time and place, the Scrum Development Team members spend a total of 15 minutes reporting to each other. Each team member summarizes what he did the previous day, what he will do today, and what impediments he faces.