Which four framework activities are found in the Extreme Programming(XP)?
A
analysis, design, coding, testing
B
planning, analysis, design, coding
C
planning, design, coding, testing
D
planning, analysis, coding, testing
Explanation: 

Detailed explanation-1: -XP describes four basic activities that are performed within the software development process: coding, testing, listening, and designing.

Detailed explanation-2: -The core framework activities of Extreme Programming (XP) process are, Planning, Coding, Testing, Design. Coding, Testing, Planning, Design.

Detailed explanation-3: -Key Practice #1 – Pair Programming. Key Practice #2 – Planning Game. Key Practice #3 – Continuous Process. Key Practice #4 – Coding Standards. Key Practice #5 – Sustainable Pace. Key Practice #6 – Test Driven Development (TDD)