EMERGING TRENDS IN SOFTWARE ENGINEERING
MISCELLANEOUS
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Which of the following is an activity that distributes estimated effort across the planned project duration by allocating the effort to specific software engineering tasks?
|
Software Macroscopic schedule
|
|
Software Project scheduling
|
|
Software Detailed schedule
|
|
None of the mentioned
|
Explanation:
Detailed explanation-1: -Project scheduling is an activity that distributes estimated effort across the planned project duration by allocating the effort to specific software engineering tasks.
Detailed explanation-2: -Explanation: The first step in project planning is to establish the objectives and scope. So option D is correct.
Detailed explanation-3: -Critical path method. The critical path method is perhaps the most popular of all methods for scheduling in construction management. It involves identifying the resources and time required to complete a milestone, as well as how the set goal is relevant to the overall project.
There is 1 question to complete.