SOFTWARE ENGINEERING

EMERGING TRENDS IN SOFTWARE ENGINEERING

MISCELLANEOUS

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
You are working as a project manager. Your Company wants to develop a project. You are also involved in planning team. What will be your first step in project planning?
A
Establish the objectives and scope of the product.
B
.Determine the project constraints
C
Select the team
D
None of the above.
Explanation: 

Detailed explanation-1: -Project initiation is the first step in starting a new project. During the project initiation phase, you establish why you’re doing the project and what business value it will deliver-then use that information to secure buy-in from key stakeholders.

Detailed explanation-2: -initiation. planning. execution. monitoring and control. closure.

There is 1 question to complete.