Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
A burn-down chart shows ____ +B12B11B10B11
|
The declining energy level of the team
|
|
The progress of the work and features completed
|
|
The number of hours worked after dark
|
|
The rate of reduction of budget for a project
|
Explanation:
Detailed explanation-1: -A burndown chart in Agile is a graphic representation of a team’s progress compared to the user story and estimated required time to complete the project. An Agile burndown chart provides a visual representation of both completed project work and the work outstanding to chart progress.
Detailed explanation-2: -A burnup chart highlights the work you’ve completed against your total project scope while a burn down chart highlights the amount of work remaining in a project. A burnup chart contains a work completed line and a project scope line.