Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
A project manager is leading a daily stand up meeting with a scrum team as part od the Direct and Manage Project Work Process. A developer raises an implement stating that he is struggling with the software code necessary to authenticate users on the sign-in page. The developer indicates that the impediment could result in a schedule delay to the current sprint.<br /><br />What is the project manager’s best course of action?
A
Write the software code for the developer since it is the project manager’s responsibility to remove impediments
B
Submit a change request to update the schedule baseline to reflect the delay caused by the impediment
C
Move the user authentication feature back into the project backlog and ask the product owner to reprioritize it
D
Recommend that the scrum team members use swarming as a technique to clear the impediment
Explanation: 

Detailed explanation-1: -Which of the following BEST describes the project manager’s role as an integrator? Put all the pieces of a project into a cohesive whole.