Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Agile:Burndown charts are used for all of the following except:
A
Helping the team understand how many points have been delivered in a given sprint
B
Helping the team understand how many points are left to be delivered before the end of a sprint
C
How many points each team member has delivered
D
Whether or not the team will deliver everything they committed to in a given sprint
Explanation: 

Detailed explanation-1: -A burndown chart has two axes, x and y. The horizontal axis represents time while the vertical axis displays user story points. The rightmost point of the chart indicates the start of a project or agile sprint while the leftmost point shows its end.

Detailed explanation-2: -There are two types of burndown charts: Agile burndown charts and sprint burndown charts. An Agile burndown chart is used by Agile teams to enable tasks to move quickly. A sprint burndown chart is used by development teams when working in short sprints.