Update the Product Backlog
|
|
Hold a Sprint Planning session
|
|
Update the Sprint Backlog
|
|
Bring up the new requirement at the next Daily Scrum
|
Detailed explanation-1: -The Product owner of your Scrum team tends to add ideas of all kind to the backlog to continue working on them at a later stage. Over time, this has lead to over 200 tickets in various stages.
Detailed explanation-2: -A product owner is responsible for ensuring the success of a project in Scrum. The product owner is responsible for managing and optimizing the product backlog in order to maximize the value of the product. A Scrum framework is an Agile methodology that facilitates communication and self-organization within a team.
Detailed explanation-3: -Product Backlog Item Overview: Each PBI must have these qualities: Description: What the goal of the PBI is. Value: the Business Value of the PBI as determined by the Product Owner. Estimate: the Team needs to estimate the relative effort it will take to move the PBI to Done.