Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
During sprint execution, when are new sprint tasks added:
A
When the product owner identifies a new task
B
When the scrum master identifies a new task
C
Never. The sprint tasks are fixed and decided during sprint planning
D
As soon as possible after they are identified, unless they reflect a scope change in the sprint goals
E
When the scrum master approves them
Explanation: 

Detailed explanation-1: -6. During Sprint Execution, when are new tasks added? Never, Sprint tasks are fixed and are decided during sprint planning. As soon as possible after they are identified, unless they reflect a scope change in sprint goals or committed Product Backlog items.

Detailed explanation-2: -The risk of introducing new work into the Sprint is that it could endanger the ability to finish work that was already included. That is what you should be most concerned about. If estimating it helps to facilitate that discussion, then you should estimate it just as you did any other task.

Detailed explanation-3: -By the end of the Sprint Retrospective, the Scrum Team should have identified improvements that it will implement in the next Sprint. Implementing these improvements in the next Sprint is the adaptation to the inspection of the Scrum Team itself.

Detailed explanation-4: -What should a Development Team do FIRST during a Sprint Planning meeting when they have realized that they have selected more than the items they can complete in a Sprint? Answer : Inform the Product Owner.