INTRODUCTION TO SOFTWARE ENGINEERING
AGILE SOFTWARE DEVELOPMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
580
|
|
20
|
|
1.07
|
|
0.933
|
Detailed explanation-1: -This means that for every estimated hour of work, the project team is only completing 0.8 hours (just over 45 minutes).
Detailed explanation-2: -The Formula for the Schedule Performance Index (SPI) SPI = EV/PV, where EV represents an earned value divided by PV representing planned value. The numerator will be the monetary value of planned work, and the denominator will be the monetary value of actual work.
Detailed explanation-3: -A good SPI is equal to or above 1, meaning you are on or ahead of schedule. In the above example, we calculated an SPI of 0.67, which indicates that the work is behind schedule. An SPI of 0.67 means that the project team only completes 0.67 hours worth of work for every hour of planned work.