It is impossible to have a contract with a customer in an agile environment/
A
True
B
False
C
Either A or B
D
None of the above
Explanation: 

Detailed explanation-1: -Therefore, it is very possible to have a contract with a customer in an Agile environment and the contract can be loosely-defined or tightly-defined. Explanation: This statement is false. The Agile Manifesto Value is “Customer Collaboration over contract negotiation”.

Detailed explanation-2: -The third value of the agile manifesto is Customer collaboration over contract negotiation. This value stresses the importance of encouraging your customers and development team to collaborate to chart the best way forward together, rather than to view each other as adversaries.

Detailed explanation-3: -An Agile Time and Materials contract allows the customer to terminate the contract at any time on the project if they do not see any added value.