Detailed explanation-1: -Purpose: A sprint review is a time to showcase the work of the team. They can be in a casual format like “demo Fridays", or in a more formal scrum meeting structure.
Detailed explanation-2: -The sprint review is a Scrum Event that takes place at the end of the Sprint to inspect the increment and adapt the product backlog. The Sprint review allows all the stakeholders to inspect and adapt to what’s already built.
Detailed explanation-3: -After the team has completed the sprint, it’s time to meet with the stakeholders in a sprint review meeting (also called an “iteration review”). The Scrum team, Scrum Master, and product owner meet with other teams, managers, and executives to showcase what they accomplished during the sprint.