INTRODUCTION TO SOFTWARE ENGINEERING
AGILE SOFTWARE DEVELOPMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
It measures variance in planned effort per story point to the actual effort per story point and is used to assess the magnitude of effort overrun or under-run at a given point in time.
|
ARBV
|
|
DPQI
|
|
SPEPI
|
|
None of the above
|
Explanation:
Detailed explanation-1: -It’s the total completed story points divided by the total number of sprints. For example, let’s say that your team finishes 50 story points in 2 sprints. Then, their sprint velocity will be (50/2) = 25 points per sprint.
Detailed explanation-2: -Story Point is a unit to measure the size of a user Story or a feature. A point is assigned to each user Story.
There is 1 question to complete.