SOFTWARE ENGINEERING

INTRODUCTION TO SOFTWARE ENGINEERING

AGILE SOFTWARE DEVELOPMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Jim is a Scrum Master on a Scrum project in a media company. His team has been asked to build a new advertising presentation component. They’ve been working together for 5 sprints and have seen increased velocity over the past two sprints. The team gets together on the first day of the sixth sprint for a planning session. In that session they use a method where the team discusses the features that will be built with the Product Owner, provide estimates on cards, and adjust their estimates as a group until they converge on a number they all agree to.<br />Which of the following BEST describes the practice they are using?
A
Planning poker
B
Convergence planning
C
Sprint planning
D
Analogous estimation
Explanation: 
There is 1 question to complete.