Plan driven software process and agile process differs in:
A
Plan driven software process and agile process differs in:
B
Plan driven process is incremental and easier to change than agile process.
C
Plan driven process progress is measured against the predefined plan, while agile process is easier to change.
D
Plan driven process responds to customer needs easier and quicker than agile process.
Explanation: 

Detailed explanation-1: -The traditional method follows a predictive model with a phased approach. It involves a top-down approach, wherein testing is executed step-by-step. Agile, on the other hand, follows a more iterative and adaptive model with stages such as project planning, risk management, design and development, and testing.

Detailed explanation-2: -Explanation: In the agile model, testers and developers work together in the project as testing is performed after every iteration, whereas in the waterfall model testing is performed once all the phases are completed.