Sandeep is a product owner on a Scrum team working on a telecommunications project. The business users let him know about a major regulatory change in one of his regular meetings with them. Handling this regulator change is now a very high priority for the team, and will need to be the main objective of the next Sprint<br />Which of the following is used to describe the main objective of the next Sprint?
A
The Increment
B
The Sprint Backlog
C
The Sprint Goal
D
The Sprint plan
Explanation: 

Detailed explanation-1: -Responsibilities of the Scrum Team They have to breakdown the requirements, create task, estimate and distribute them. In other words this means that they have to create the Sprint Backlog. They have to perform the short Daily Sprint Meeting.

Detailed explanation-2: -One of the most important responsibilities for a scrum product owner is managing the product backlog. This is the development team’s project to-do list. The product owner’s responsibility is to create the list of backlog items and prioritize them based on the overall strategy and business objectives.