The agile triangle of constraints is said to be inverted from the traditional triangle because it allows:
|
Scope and time to vary instead of cost
|
|
Cost and time to vary instead of scope
|
|
Scope and cost to be fixed instead of time
|
|
Scope to vary while time and cost are fixed
|
Explanation:
Detailed explanation-1: -The traditional iron triangle focuses on three elements; scope, cost, and schedule. On the other hand, agile triangle focuses on value, quality, and constraints. Constraints include scope, cost, and schedule. You need software, for instance, that can manage a school’s library system.
Detailed explanation-2: -Scope is about the volume of work assigned. Time is about the duration available to do it. Cost refers to the number of resources you want to devote to the task. Quality is about the resultant quality of the output.