SOFTWARE ENGINEERING

INTRODUCTION TO SOFTWARE ENGINEERING

AGILE SOFTWARE DEVELOPMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
A
Progressive Elaboration
B
Sprint Review
C
Product Backlog
D
Product Owner
Explanation: 

Detailed explanation-1: -Progressive elaboration is an iterative process in project management knowledge, which the details of project management plan and amount of information will increase. In this process initial estimates of items such as project scope description, planning, budget, etc. will become more accurate.

Detailed explanation-2: -Progressive elaboration involves continuously improving and detailing a plan as more detailed and specific information and more accurate estimates become available.

There is 1 question to complete.