SOFTWARE ENGINEERING

INTRODUCTION TO SOFTWARE ENGINEERING

AGILE SOFTWARE DEVELOPMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
The Kanban pull system means that?
A
Kanban team members “pull” work from each other, pairing up as needed.
B
Each time a work item is completed, the next work item is “pulled” into that stage of the process
C
Iterations are “pulled” into the process as needed to keep the work organized.
D
Kanban tams have shorter work queues, which means that the work takes longer to complete (as shown by Little’s Law).
Explanation: 

Detailed explanation-1: -Push is also called “make to stock, ‘’ wherein products are delivered based on assumptions of what the customer might want. Pull, on the other hand, is also called “make to demand, ‘’ where production is based on customer demand. So, in a push system, the products are made, stocked, and marketed to possible consumers.

Detailed explanation-2: -The first step in implementing a Kanban system is to identify the steps in your current workflow. This requires participation from everyone in your team. As a group, talk through how work travels from “To Do” to “Done.”