Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
The program board highlights feature delivery dates, milestones, and what else for Agile Release Train teams?
A
Requirements
B
Timeboxes
C
Dependencies
D
Objectives
Explanation: 

Detailed explanation-1: -The SAFe program board is an integral component of PI planning. In fact, it’s the key deliverable that should come out of a PI session. The program board highlights delivery dates, dependencies among teams, milestones, and timelines.

Detailed explanation-2: -The Agile Release Train meeting (Art-Sync) helps to follow up the progress of the program and to solve important problems (impediments). The following is handled in this meeting: Global progress on objectives and features. Risks and issues that need to be escalated to other teams or to the program level.

Detailed explanation-3: -A release train engineer (RTE) is a servant leader who facilitates program level processes and execution, drives continuous development, manages risks and escalates impediments while also acting as a full time chief scrum master for a Scaled Agile Framework (SAFe).