Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
Increment
|
|
Review
|
|
Ideal time
|
|
Velocity
|
Detailed explanation-1: -Simply add up the total of story points completed from each sprint, then divide by the number of sprints. So, your average sprint velocity is 96 รท 3 = 32. You can now base the amount of work to be done in future sprints on the average of 32 story points.
Detailed explanation-2: -Velocity is a measure of the amount of work a Team can tackle during a single Sprint and is the key metric in Scrum. Velocity is calculated at the end of the Sprint by totaling the Points for all fully completed User Stories.
Detailed explanation-3: -Types of Velocity in Scrum Actual velocity is calculated by dividing the total Story Points completed by the team by the number of Sprints. For instance, if the Scrum Team has finished a total of 80 points over 4 Sprints then the actual velocity of the team would be 20 points per Sprint.