Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
What are the two inputs to PI Planning? (Choose two)
|
Vision
|
|
Ready user stories
|
|
Program Roadmap
|
|
Top-10 Features list
|
|
A set of PI Objectives
|
Explanation:
Detailed explanation-1: -Business context (see ‘content readiness’ below) Roadmap and vision. Highest priority Features of the ART Backlog. 19-Mar-2023
Detailed explanation-2: -The Solution Roadmap, vision, Solution Intent, and the top Capabilities from the Solution Backlog are all inputs to the pre-and post-PI planning process.
Detailed explanation-3: -2 full day events run every 8-12 weeks (depending on the length of your increments) Product Managers work to prioritize the planned features for the increment beforehand. Development teams own user story planning and estimation. More items