What is meant by “Yesterday’s Weather” in an Agile project?
|
Teams work less well when it rains
|
|
Keeping metrics of earlier work to help with future estimates
|
|
Retrospectives should include less important topics such as the weather
|
|
Estimating is as futile as predicting the weather
|
Explanation:
Detailed explanation-1: -Clear skies. Low 67F. Winds ENE at 10 to 15 mph.
Detailed explanation-2: -Which one of the following is a key feature that you would expect to find in an Agile project? All documentation done in previous projects would be replicated for the Agile project.
Detailed explanation-3: -When forming an Agile project team it is BEST to use: Answer : Generalized Specialists.