What is the main task of a tester in a backlog grooming meeting?
A
To Confirm the Acceptance Criteria that will validate and test for all items.
B
To Include the test method outlined in the Test Planning
C
To outline dependencies, determine time, accurately determine testability, and expose shortcomings in the scope.
D
all options given
Explanation: 

Detailed explanation-1: -During Backlog Refinement (Grooming) the Scrum Master facilitates as the Product Owner and Scrum Team review the user stories at the top of the Product Backlog in order to prepare for the upcoming sprint. Backlog Refinement (Grooming) provides the first input to Sprint Planning.

Detailed explanation-2: -Backlog grooming is a regular session where backlog items are discussed, reviewed, and prioritized by product managers, product owners, and the rest of the team. The primary goal of backlog grooming is to keep the backlog up-to-date and ensure that backlog items are prepared for upcoming sprints.

Detailed explanation-3: -The objective is to be in a position where for any piece of work presented in planning you know exactly what the work requires. You should then have a good idea of what you will test and therefore provide reliable estimates. If this is not the case, then the work cannot be effectively planned into the sprint.