Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
It is a meeting to inspect the Increment and adapt the Product Backlog if needed
|
|
It is a meeting where the Development Team synchronizes activities and creates a plan for the next 24 hours
|
|
It is an opportunity for the Scrum Team to inspect itself and create a plan for improvements to be enacted during the next Sprint
|
|
It is the key inspect and adapt meeting
|
Detailed explanation-1: -The Sprint Retrospective is an opportunity for the Scrum Team to inspect itself and create a plan for improvements to be enacted during the next Sprint. The Sprint Retrospective occurs after the Sprint Review and prior to the next Sprint Planning. This is at most a three-hour meeting for one-month Sprints.
Detailed explanation-2: -Sprint Retrospective is a formal opportunity for the Scrum Team to inspect everything that happened in the Sprint and create a plan to improve and implement during the sprint. Learning and improvement are continuous. Scrum believes in continuous learning and continuous improvement.
Detailed explanation-3: -The purpose of a Sprint Retrospective is to identify potential pitfalls and mistakes, evaluate the past working cycle and define actions that may improve things. A Sprint Retrospective is like a safe space for people to share honest feedback. It is an opportunity to focus on inspection and adaptation.
Detailed explanation-4: -Sprint Retrospective is a meeting where all the team members sit and retrospect from their current sprint and lay out the action items to improvise for the upcoming sprints. For the very same reason, Sprint Retrospective is conducted at the end of each Sprint.