INTRODUCTION TO SOFTWARE ENGINEERING
AGILE SOFTWARE DEVELOPMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
Get more developers onboard
|
|
Seek help from the other Scrum Team Members
|
|
Work overtime
|
|
Take a call to remove some of the Sprint Backlog Items
|
Detailed explanation-1: -What should a Development Team do FIRST during a Sprint Planning meeting when they have realized that they have selected more than the items they can complete in a Sprint? Answer : Inform the Product Owner.
Detailed explanation-2: -As the Developers work during the Sprint, they keep the Sprint Goal in mind. If the work turns out to be different than they expected, they collaborate with the Product Owner to negotiate the scope of the Sprint Backlog within the Sprint without affecting the Sprint Goal.
Detailed explanation-3: -As the development team start work during the sprint, it realize it has selected too much work to finish in the sprint. What should it do? d. As soon as possible in the sprint, work with product owner to remove some work of product backlog items.