Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
When can a Sprint be canceled:
A
The Sprint items are no longer needed
B
Sprint can never be canceled
C
When Development is unable to complete the work
D
Whenever the Scrum Master says
E
Whenever the Product Owner says
Explanation: 

Detailed explanation-1: -Q #5) When can a Sprint be canceled? The power to cancel the Sprint lies only with the Product Owner. He/She can call to cancel an ongoing Sprint when the Sprint Items are no longer required by the business i.e. the items have become obsolete.

Detailed explanation-2: -A Sprint can be cancelled before the Sprint time-box is over. Only the Product Owner has the authority to cancel the Sprint, although he or she may do so under influence from the stakeholders, the Development Team, or the Scrum Master. A Sprint would be cancelled if the Sprint Goal becomes obsolete.

Detailed explanation-3: -A Sprint can be canceled before the Sprint time-box is over. Only the product owner has the authority to cancel the Sprint. A Sprint would be canceled if the Sprint goal becomes obsolete. Sprint cancellations consume resources as everyone has to regroup in another Sprint Planning Meeting to start another Sprint.