Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
When is a Scrum Sprint over?
A
When the team finishes the work
B
When the team completes the Sprint Retrospective
C
When the timebox expires
D
When the team completes the Sprint Review
Explanation: 

Detailed explanation-1: -A Sprint, like the other Scrum Events, is time-boxed. This means that the event must be completed within a certain time frame. Accordingly, the Sprint ends as soon as the time box has expired-even if the product increment is not completely finished.

Detailed explanation-2: -A sprint is a short, time-boxed period when a scrum team works to complete a set amount of work.

Detailed explanation-3: -no, the Sprint ends when the timebox expires. Unfinished Sprint Backlog Items go back to the Product Backlog and can be addressed in the following Sprint.-of reduced complexity due to the consistency of the Scrum Events (no need to reschedule meetings etc.)

Detailed explanation-4: -Sprint Ends once the Sprint time-box expires. Ideally all the sprint ceremonies should have been completed. Any spill over of ceremonies and PBI in WIP needs to be moved to next sprint keeping Product owner in confidence.

There is 1 question to complete.