Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
When is a Sprint over
|
When all Sprint Backlog items are done
|
|
When the timebox expires
|
|
When all Sprint Backlogs tasks are done
|
|
When the Product Owner considers it done, with any appropriate reason
|
Explanation:
Detailed explanation-1: -One of the questions in the Scrum Open assessment asks about the proper time to consider a Sprint as “over”. The correct answer for this particular question is “When the time-box expires”.
Detailed explanation-2: -The short and simple answer is that a sprint is over when the sprint timebox ends! (at whatever cadence the team has chosen for the sprints, i.e. two weeks, one month, one week, etc).
Detailed explanation-3: -no, the Sprint ends when the timebox expires. Unfinished Sprint Backlog Items go back to the Product Backlog and can be addressed in the following Sprint.-of reduced complexity due to the consistency of the Scrum Events (no need to reschedule meetings etc.)