Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
When must a new increment of working software be available
A
Before each planned release
B
Every 3 sprints
C
At the end of each sprint
D
Whenever the user acceptance testing is done
E
When the product owner asks for it
Explanation: 

Detailed explanation-1: -It helps you reduce the risk of undone work by making transparent all that is needed to create “Done” increments every Sprint. It will also make very transparent all the impediments that are getting in the way of achieving this goal.

Detailed explanation-2: -A “Done” increment is required at the Sprint Review. At the end of a Sprint, the new Increment must be “Done, ‘’ which means it must be in useable condition and meet the Scrum Team’s definition of “Done”. Development Teams deliver an Increment of product functionality every Sprint.

There is 1 question to complete.