Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
When should a Sprint Goal be created? (Choose the best answer.)
A
It should have been created in the previous Sprint during Product Backlog refinement
B
It must be established before Sprint Planning in order to begin planning
C
A Sprint Goal is not mandatory in Scrum
D
At any time during the Sprint
E
During Sprint Planning
Explanation: 

Detailed explanation-1: -A Sprint Goal is created during the Sprint Planning process, and this allows different team members to collaborate effectively beneath one shared mission. While the Sprint Goal represents a commitment by the Scrum team, it provides flexibility, allowing individuals to figure out how they can best achieve the goal.

Detailed explanation-2: -The sprint goal is a mandatory part of the Scrum framework. It is collaboratively created by the Scrum team during the sprint planning meeting. Its creation is typically guided by the product owner with the development team then deciding which functionality and technology it will implement to fulfil the goal.

Detailed explanation-3: -What is sprint planning? Sprint planning is an event in scrum that kicks off the sprint. The purpose of sprint planning is to define what can be delivered in the sprint and how that work will be achieved. Sprint planning is done in collaboration with the whole scrum team.

Detailed explanation-4: -The whole Scrum Team then collaborates to define a Sprint Goal that communicates why the Sprint is valuable to stakeholders. The Sprint Goal must be finalized prior to the end of Sprint Planning.