Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
When all Product Backlog items meet their definition of done
|
|
When the time-box expires
|
|
When all the tasks are completed
|
|
When the product Owner says it is completed
|
Detailed explanation-1: -A Sprint, like the other Scrum Events, is time-boxed. This means that the event must be completed within a certain time frame. Accordingly, the Sprint ends as soon as the time box has expired-even if the product increment is not completely finished.
Detailed explanation-2: -Sprints end only when the timebox elapses or the Product Owner cancels the Sprint.
Detailed explanation-3: -The Sprint is an event that does not get extended. A “done” Increment of product is due by the end of the Sprint.
Detailed explanation-4: -A Sprint can be canceled before the Sprint time-box is over. Only the product owner has the authority to cancel the Sprint. A Sprint would be canceled if the Sprint goal becomes obsolete. Sprint cancellations consume resources as everyone has to regroup in another Sprint Planning Meeting to start another Sprint.