Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
XP as Scrum are 2 to 4 weeks whereas XP is 1 to 2 months
|
|
Scrum as they are 2 to 4 weeks whereas XP is 1 to 2 weeks
|
|
Either A or B
|
|
None of the above
|
Detailed explanation-1: -Scrum is commonly associated with self-organizing teams. It also usually has sprints that are 2 to 4 weeks long, while XP iterations are shorter, taking 1 to 2 weeks.
Detailed explanation-2: -Comparison. First of all, both Scrum and XP aim to deliver a high-quality product to the client as fast as possible. Although Scrum focuses on management and productivity, whereas XP concentrates on software quality and engineering techniques. Secondly, frameworks have few differences when it comes to Sprints.
Detailed explanation-3: -It is typically two to four weeks in duration and each sprint starts the moment the previous one is completed. The Scrum sprint cycle is often referred to as a process of continuous development. It delivers a consistent work cadence for product releases and keeps the project’s momentum going until complete.