Which of the following is an estimated cost for delivering a single point based on past performance of the delivering Organization?
A
Cost per point
B
Baseline Velocity
C
Product backlog in points
D
Planned Value
Explanation: 

Detailed explanation-1: -The three types of cost estimates are design, bid, and control estimates. Design estimates are prepared in the project preliminaries which gives the order of magnitude of the project cost.

Detailed explanation-2: -The four major analytical methods or cost estimation techniques used to develop cost estimates for acquisition programs are Analogy, Parametric (Statistical), Engineering (Bottoms Up), and Actual Costs.