Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following is delivered at the end of the Sprint?
A
A document containing test cases for the current sprint
B
An architectural design of the solution
C
An increment of Done software
D
Wireframes designs for User Interface
Explanation: 

Detailed explanation-1: -Q #1) Which of the following is delivered at the end of the Sprint? The output of every Sprint is an Increment of a Done Software which can be shipped off to the end user for usage. An item is only marked done if it matches the definition of done.

Detailed explanation-2: -Learn About Agile This means that at the end of each sprint, the team has produced a coded, tested and usable piece of software. So at the end of each sprint, a sprint review meeting is held. During this meeting, the Scrum team shows what they accomplished during the sprint.

Detailed explanation-3: -The sprint review is a Scrum Event that takes place at the end of the Sprint to inspect the increment and adapt the product backlog. The Sprint review allows all the stakeholders to inspect and adapt to what’s already built.