Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following is NOT a Scrum event?
A
Sprint Review
B
Product Backlog
C
Retrospective
D
Daily Scrum
Explanation: 

Detailed explanation-1: -Contrary to popular misunderstanding, the Product Backlog does not contain “user stories”; it simply contains items. Those items can be expressed as user stories, use cases, or any other requirements approach that the group finds useful.

Detailed explanation-2: -Sprint Planning, the Daily Scrum, Sprint Review and the Sprint Retrospective all occur within the sprint. There are no special Sprints.