Which of the following is the average time between delivery of completed work items?
|
Velocity
|
|
Lead Time
|
|
Cycle Time
|
|
Lag Tim
|
Explanation:
Detailed explanation-1: -Cycle time is often reported to project leaders or clients as an average. For example, producing a particular report might have an average cycle time of five business days.
Detailed explanation-2: -: the time required to complete a cycle. used especially in connection with time and motion studies.
Detailed explanation-3: -The inventory between the start and the end points of a production system (not counting crib inventory or finished goods inventory) is called work-in-process (WIP). The cycle time (CT) of a given production system is the average time parts spend as WIP.