Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Who can abnormally terminate a Sprint? (Choose the best answer.)
A
The Scrum Master
B
The Development Team or its members
C
The Product Owner
D
The Stakeholders
Explanation: 

Detailed explanation-1: -Not only can the Product Owner abnormally terminate a Sprint at any time, but the ScrumMaster can cancel the Sprint at any time on his or her accord or on behalf of either the Team or the Product Owner.

Detailed explanation-2: -Only the Product Owner has the authority to cancel the Sprint. A Sprint would be cancelled if the Sprint Goal becomes obsolete. This might occur if the company changes direction or if market or technology conditions change. In general, a Sprint should be cancelled if it no longer makes sense given the circumstances.

Detailed explanation-3: -A Sprint could be cancelled if the Sprint Goal becomes obsolete. Only the Product Owner has the authority to cancel the Sprint. This opens it up to the Scrum Team to decide what comes next should a Sprint Goal become obsolete, and the PO decide to cancel a Sprint.

Detailed explanation-4: -A Sprint would be cancelled if theSprint Goal becomes obsolete. This might occur if the company changes direction or if marketor technology conditions change.