Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
who is responsible for the product backlog and decides which tasks has priority?
A
The Product Owner
B
The Scrum Master
C
The Development Team
D
None of the above
Explanation: 

Detailed explanation-1: -Because the product owner is the sole Scrum team member in charge of prioritizing the product backlog – determining which features are prioritized for the next production sprint – the product owner controls the direction of the project at any given point in time.

Detailed explanation-2: -The product owner’s responsibility is to develop and communicate the product goal, create and clearly communicate product backlog items, and order the backlog to maximize business value.

Detailed explanation-3: -The product owner is responsible for managing and optimizing the product backlog in order to maximize the value of the product. A Scrum framework is an Agile methodology that facilitates communication and self-organization within a team. A Product Owner is part of the scrum team.

Detailed explanation-4: -Product backlog management falls to the product manager, who has the key responsibility to create, prioritize, and maintain it.