Your Scrum team began measuring velocity over the past three sprints and recorded the following numbers:30, 42, 23. What can you tell about the team from these measurements?
A
The team is still determining its story point scale
B
The team is becoming less productive and actions must be taken to correct this
C
The velocity is evening out over multiple sprints
D
The velocity has not been measured correctly
Explanation: 

Detailed explanation-1: -Velocity is a useful measure of the value a Scrum Team produces. Forming teams and keeping them together is a good strategy for increasing utilization rates. In an organization using Scrum, the manager ist still responsible for the quality of the product.

Detailed explanation-2: -Calculate the maximum total available hours of all team members for a two-week sprint period. Then, calculate the capacity loss. Now, get the ratio of your adjusted capacity to your maximum capacity. And finally, you multiply his with your average velocity. 24-Jun-2022