Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
During which project management phase, communication is a paramount key?
A
Planning phase
B
Design phase
C
Construction & operation phase
D
All phases
Explanation: 

Detailed explanation-1: -Phase 2: Project planning In this phase, the primary tasks are identifying technical requirements, developing a detailed project schedule, creating a communication plan, and setting up goals/deliverables.

Detailed explanation-2: -Plan communications. Manage communications. Control communications. 18-Mar-2022