SOFTWARE ENGINEERING

INTRODUCTION TO SOFTWARE ENGINEERING

OVERVIEW OF SOFTWARE ENGINEERING

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
The first step in project planning is to
A
determine the budget.
B
select a team organizational mode
C
determine the project constraints
D
establish the objectives and scope.
Explanation: 

Detailed explanation-1: -The first step in the project planning phase is to define the goals and objectives of your project. Project goals and objectives help you decide if the project should be prioritized (or even undertaken-essentially you need to use a proof of concept).

Detailed explanation-2: -initiation. planning. execution. monitoring and control. closure.

Detailed explanation-3: -Think of your plan as a roadmap for stakeholders. Break the project into a list of deliverables. Talk to your team. Identify risks. Create a budget. Add milestones. Set progress reporting guidelines.