What are the component should be in the Software Development Team, except:
A
A Project Manager
B
A UI Designer
C
A Business Analyst
D
A Programmer and or A Tester
Explanation: 

Detailed explanation-1: -Which of the following is not considered as a risk in project management? Explanation: Testing is a part of project, thus it can’t be categorized as risk.

Detailed explanation-2: -Baselines for scope, schedule, and cost. Management plans for scope, schedule, cost, quality, human resources, communications, risk, and procurement. Requirement management plan. Change management plan. Configuration management plan. Process improvement plan. 06-Apr-2023